HILTON Redevelopment Project, MaltaYacht marina breakwater with double corrosion protected DYWIDAG bar anchorsThis project required to create an artificial yacht harbour. After three harbour bays were blasted and hydro jetted out of the bedrock, the entry to the sea was opened. For harbour protection a 50m long breakwater was constructed out of precast elements. These elements had to be secured against waves from strong north-east winds. The harbour planning firm SCORTINO, Italy required that the precast elements be tied down with 240 pieces 36mm dia. double corrosion protected DYWIDAG bar anchors (DCP), each 32m long, securing the 24 segments to the sea bed. Twelve more anchors were used to tie down the smaller, so called inner wave breaker. |