Downloads
Rehabilitation Works during Construction of the Chienberg Tunnel, SissachThe 2.3 km long Chienberg Tunnel is the principal element of the 3.5 km long Sissach ring road scheduled for completion in 2006Construction of the Chienberg Tunnel began in 1998. In January 2000, during the process of mining the tunnel, a number of technical problems were encountered. Between the fall of 2002 and January 2004, uplifts of the tunnel floor measuring nearly 10 cm discovered at tunnel meter 880 during the process of conducting routine measurements posed yet another problem. Based on model calculations uplifts of this magnitude had only been expected in 50 to 100 years. |