| Construction of the Augustaburg Tunnel on the new Nuremberg-Berlin High-Speed Railway LineOn September 11, 2002 construction began on the 3.61 km long section of the German Unity Transport Project "Track No.8.1" west of Erfurt.. Among other things, this section includes the 300m long Geratal bridge and the 1.4 km long Augustaburg tunnel. The capital spending volume for the tunnel construction is EUR 40 million. Augustaburg-TunnelThe 1.4 km long tunnel is a reinforced concrete tube with separate internal and external leafs. The tunnel cross-section is designed for two-track utilization on ballast less track. Slope stabilization at the northern entranceA 55,000m3 cut was excavated at the northern entrance. The excavation was stabilized as a slope on the right-hand side and as an abrupt topographical change on the opposite side by means of an anchored retaining wall. |