Ready for the Future: DYWIDAG Strand Anchors with DYNA Force® Sensors secure Grančarevo Dam

The Grančarevo Dam is located on the Trebišnjica River in the south-east of Bosnia and Herzegovina near its border with Montenegro. With a height of 123m, this arch dam, near the town of Gornje Grančarevo in the municipality of Trebinije, is the country's highest dam. The adjacent Bileća Reservoir is the largest reservoir in Bosnia and Herzegovina in terms of active storage.

The Grančarevo Dam went into operation in 1967, and the two hydroelectric power plants, Trebinije-1 and -2, with a total output of 188MW were completed in 1968 and 1979.

Recently, the monitoring systems for the safety of the dam were rehabilitated and modernized. In order to ensure the long-term stability of the dam, permanent Type 12-0.62 DYWIDAG double corrosion protected Strand Anchors were installed in the right flank of the slope directly underneath the arch dam. The anchors used were electrically testable El-Iso Strand Anchors in lengths of up to 61.5m. This system has been approved for permanent use (applications with 100+ year design life).

By electrically uncoupling the anchor head and the tendon from the anchor plate, a resistance test between the anchor and the soil can be carried out - the integrity of the corrosion protection sheathing can be tested at any point of time in the future by the use of standardized resistance tests. Furthermore, the El-Iso System complies with SIA requirements.

In order to allow the owner to continuously monitor the prestressing forces in the strand anchors, 46 DYNA Force® Sensors were installed in the bond length of 23 anchors. The DYNA Force® Sensors also provided an additional mechanism for monitoring the forces during tensioning. Additionally, DSI supplied 4 multiplexers with a stainless steel casing for permanent outdoor use that were connected to the DYNA Force® Sensors in the anchors. Furthermore, DSI engineers installed a readout unit and a controller to automatically read the data. The data measured by the DYNA Force® Sensors are continuously read and saved by a controller that is connected to the readout unit. The data is transferred via a glass fiber connection with the controller to a computer located in the control room and analyzed once a month. The control room serves for the centralized monitoring of the complete dam.

The strand anchors supplied by DSI were tensioned using two coupled Hollow-Piston CFRP Cylinders. For additional protection, greased stainless steel caps were installed over the anchor heads.

Thanks to the type El-Iso Strand Anchors that were used, the slope underneath the Grančarevo Dam will be permanently monitored to help ensure the safety and reliability of the acting forces.

 

 

Owner

HET (Hidroelektrane na Trebišnjici), Bosnia and Herzegovina
General

Contractor

Geosonda d.o.o. Zenica, Bosnia and Herzegovina
Subcontractor: HISTEH d.o.o., Slovenia


Consulting

Engineers IBE d.d., Slovenia


DSI Unit

DYWIDAG-Systems International GmbH, Austria


DSI Scope

Production, supply, technical support, supervision


DYWIDAG Products

Permanent Type 12-0.62, up to 61.5m long DYWIDAG Strand Anchors with double corrosion protection, El-Iso System, 46 DYNA Force® Sensors, 4 multiplexers, 1 readout unit, 1 controller 